Thursday, January 17, 2008

Schedule and Milestones

Milestones

Description

Milestone Criteria

Planned Date

M0

Start Project

<2008-01-04>

Start-up meeting

Got the requirements.

<2008-01-04>

M1

Start Planning

<2008-01-07>

Write thesis project plan

thesis project plan ready

<2008-01-07>

M2

First iteration start

<2008-01-08>

Install Trac and related software on the Linux-server.

Browsing tickets, sorting tickets, viewing a ticket

user interfaces created, coding of functionality finished

<2008-01-31>

M3

Second iteration start

<2008-02-01>

Creating new tickets

user interfaces created, coding of functionality finished

<2008-02-23>

M4

third iteration start

<2008-02-26>

Commenting a ticket

user interfaces created, coding of functionality finished

<2008-03-14>

M5

forth iteration start

<2008-03-17>

Hiding tickets, testing the system, finish writing thesis.

add attachment (if have time)

user interfaces created, coding of functionality finished, thesis ready

<2008-03-31>

M6

System acceptance testing ,

Return thesis to supervisor

System tested by users, thesis marked by supervisor

<2008-04-01>

fix system,

correct the thesis

<2008-04-15>

M7

Close Project


<2008-04-20>